RICHMOND, Va. – Virginia voters will go to the polls on June 13 to select nominees for governor. For those that care about the human and environmental health of Virginia, and for those that have devoted their lives to stopping the ill-advised Atlantic Coast Pipeline and Mountain Valley Pipeline, the Appalachian Chronicle believes the evidence is clear – Democratic candidate Tom Perriello is the best choice for Virginians and their neighbors.

While the race will be watched closely with those obsessed about reading political tea leaves and what it means about upcoming national election cycles in 2018 and 2020, many folks in Virginia – as well as neighboring West Virginia and North Carolina – have far more immediate concerns. They wish to protect their families, homes and communities from the inevitable, permanent and negative impacts upon human and environmental health that will be caused by the pipelines.

Mr. Perriello is an ally of those fighting fracking and the pipelines. He has issued position papers on the environment and building a clean energy future which are based in sound science and reject profit over people. Indeed, in taking on Richmond-based Dominion Energy, he has clearly demonstrated courage.

On Leadership

What would induce anyone, at this stage, to hold on to power only to be remembered for their inability to take action when it was urgent and necessary to do so?” – Pope Francis

A couple of years ago, I was asked by a well-known environmental group to speak to the relevance of the ecological encyclical “On Care for Our Common Home” by Pope Francis as it applies to Appalachia.

This group clearly understands the root cause of the problems we face. It didn’t take long for several people to assert that the most important statement in the encyclical was not about the environment, but leadership. In paragraph 57 of the encyclical, Pope Francis asks, “What would induce anyone, at this stage, to hold on to power only to be remembered for their inability to take action when it was urgent and necessary to do so?” In fact, as his is blunt nature, the pope said also, “We lack leadership” (no. 53).

That is the first reason Virginia and Appalachian residents need Mr. Perriello to be the next governor of Virginia. He has demonstrated the leadership required by the times.

Shenandoah Mountain

Shenandoah Mountain, Va. If approved, the Atlantic Coast Pipeline would forever mar this land. Photo by Brad Striebig. 

The second reason is that the state agencies charged with protecting the environment are simply not doing it. Dozens of groups and thousands of residents of Virginia have been denied critical information. Mr. Perriello has promised to return transparency and proper enforcement to Virginia government. One example of why this is so critical just came in from Rick Webb, the program coordinator for the Dominion Pipeline Monitoring Coalition, based in Monterey.

In an email, Webb wrote, “The Virginia Department of Environmental Quality announced on April 6th that it would conduct full, site-specific regulatory reviews for both the Atlantic Coast Pipeline and the Mountain Valley Pipeline under the Clean Water Act and state law.” He revealed, however, “DEQ officials now say (seven weeks later) that inaccurate information was provided to the public, and that the DEQ will instead rely on the U.S. Army Corps of Engineers to examine stream crossings, which will number in the hundreds for each project.”

Webb continued, “DEQ’s current backpedaling is but the latest manifestation of Dominion’s resistance to providing site-specific plans for agency and public review. Dominion doesn’t want the public to understand the real impact of the project until after it has its approvals in hand. The same is no doubt true for the MVP developers.”

Mr. Perriello has pledged to require state agencies to do their jobs. That begins with holding Dominion and its partners accountable. To that end, we are hopeful that Mr. Perriello would embrace the Precautionary Principle to justify placing a moratorium on pipeline development, fracking and related activities.

The Precautionary Principle, according to the Science & Environmental Health Network, asserts, “When an activity raises threats of harm to human health or the environment, precautionary measures should be taken even if some cause and effect relationships are not fully established scientifically. In this context the proponent of an activity, rather than the public, should bear the burden of proof.” It is a philosophy embraced by public and environmental health experts the world over.

Pope Francis

Pope Francis

As Pope Francis wrote, “This precautionary principle makes it possible to protect those who are most vulnerable and whose ability to defend their interests and to assemble incontrovertible evidence is limited. If objective information suggests that serious and irreversible damage may result, a project should be halted or modified, even in the absence of indisputable proof. Here the burden of proof is effectively reversed, since in such cases objective and conclusive demonstrations will have to be brought forward to demonstrate that the proposed activity will not cause serious harm to the environment or to those who inhabit it” (no. 186).

This is the third reason that we support Mr. Perriello. His many position papers demonstrate an overarching, preferential concern for the poor and vulnerable.

Mr. Perriello has demonstrated leadership. He is standing with the people. We hope the people of Virginia will stand with him on Election Day – in June and November.”

Mr. Perriello has risked his political career by aligning himself with the people, with human health, and with the environment in direct defiance of the wishes of Dominion Energy. This election is an opportunity for the people of Virginia to honor not Dominion, but the best characteristics of the Old Dominion – concern for one’s neighbor, an understanding of the value and beauty of the land, and a fierce determination to maintain individual liberty.

A vote for Mr. Perriello will accomplish that. His courage is rare and a good reason alone to endorse him. He is clearly the best candidate to protect human and environmental health. Finally, he understands that our problems are symptomatic of a much more dangerous problem our nation faces – the lack of solid, authentic, courageous leaders. Well, Mr. Perriello has demonstrated leadership. He is standing with the people. We hope the people of Virginia will stand with him on Election Day – in June and November.

© The Appalachian Chronicle, 2017.

On Facebook

On Twitter: @appchronicle

ACP Would Require Extensive Mountaintop Removal

Proposed route by Dominion would destroy nearly 40 miles of ridgetops, cause ‘irrevocable harm,’ say environmental groups

RICHMOND, Va. – A briefing paper released today details how Dominion Resources intends to blast away, excavate, and partially remove entire mountaintops along 38 miles of Appalachian ridgelines as part of the construction of the Atlantic Coast Pipeline (ACP).

There is no way around it. It’s a bad route, a bad plan, and should never have been seriously considered.” – Dan Shaffer, Spatial Analyst with the Dominion Pipeline Monitoring Coalition

CCAN logoThe briefing paper was prepared by the Chesapeake Climate Action Network in coordination with the Allegheny-Blue Ridge AllianceFriends of Nelson, Appalachian Mountain Advocates, and the Dominion Pipeline Monitoring Coalition. It cites data from the Draft Environmental Impact Statement (DEIS) prepared by the Federal Energy Regulatory Council (FERC) as well as information supplied to FERC by Dominion. It also compiles information from Geographic Information System (GIS) mapping software and independent reports prepared by engineers and soil scientists.

They found that Dominion would require mountaintops to be “reduced” by 10 to 60 feet along the proposed route of the pipeline. For perspective, the height equivalent of a five-story building would be erased in places from fully forested and ancient mountains.

ABRA-Logo-Square-100-1Furthermore, Dominion has yet to reveal how it intends to dispose of at least 247,000 dump-truck-loads of excess rock and soil – known as “overburden” – that would accumulate from the construction along just these 38 miles of ridgetops.

It is astounding that FERC has not required Dominion to produce a plan for dealing with the millions of cubic yards of excess spoil that will result from cutting down miles of ridgetop for the pipeline. We know from experience with mountaintop removal coal mining that the disposal of this material has devastating impacts on the headwater streams that are the lifeblood our rivers and lakes.” – Ben Luckett, Staff Attorney at Appalachian Mountain Advocates

“In light of the discovery that the ACP will cause 10 to 60 feet of mountaintops to be removed from 38 miles of Appalachian ridges, there is nothing left to debate,” said Mike Tidwell, Executive Director of the Chesapeake Climate Action Network. “Dominion’s pipeline will cause irrevocable harm to the region’s environmental resources. With Clean Water Act certifications pending in both Virginia and West Virginia, we call on Virginia Governor Terry McAuliffe and West Virginia Governor Jim Justice to reject this destructive pipeline.”

MTR 2_OVEC

Mountaintop Removal – Courtesy of OVEC

Dominion has submitted a proposal to FERC to build a 42-inch diameter pipeline that would transport natural gas from West Virginia into Virginia and North Carolina. The groups assert that Dominion has attempted to paint the ACP as an “environmentally-friendly” project. However, they argue that proposed construction methods and route selection across and along steep mountains is unprecedented for the region – if not the country – and are viewed as extreme and radical by landowners, conservationists, and engineers. Similar impacts – although not yet fully inventoried – could come from the construction of a second pipeline to the south: the Mountain Valley Pipeline led by the company EQT Midstream Partners, LP.

Friends of Nelson“The ACP could easily prove itself deadly,” said Joyce Burton, Board Member of Friends of Nelson. “Many of the slopes along the right of way are significantly steeper than a black diamond ski slope. Both FERC and Dominion concede that constructing pipelines on these steep slopes can increase the potential for landslides, yet they still have not demonstrated how they propose to protect us from this risk. With all of this, it is clear that this pipeline is a recipe for disaster.”

Key findings of the report include:

  • Approximately 38 miles of mountains in West Virginia and Virginia will see 10 feet or more of their ridgetops removed in order to build the ACP; this figure includes 19 miles each in West Virginia and Virginia.
  • The majority of these mountains would be flattened by 10 to 20 feet, with some places along the route requiring the removal of 60 feet or more of ridgetop.
  • Building the ACP on top of these mountains will result in a tremendous quantity of excess material, known to those familiar with mountaintop removal as “overburden.”
  • Dominion would likely need to dispose of 2.47 million cubic yards of overburden, from just these 38 miles alone.
  • Standard-size, fully loaded dump trucks would need to take at least 247,000 trips to haul this material away from the construction site.

APPALMAD-LOGO-223Ben Luckett, Staff Attorney at Appalachian Mountain Advocates, said, “It is astounding that FERC has not required Dominion to produce a plan for dealing with the millions of cubic yards of excess spoil that will result from cutting down miles of ridgetop for the pipeline. We know from experience with mountaintop removal coal mining that the disposal of this material has devastating impacts on the headwater streams that are the lifeblood our rivers and lakes.” He argued, “FERC and Dominion’s complete failure to address this issue creates a significant risk that the excess material will ultimately end up in our waterways, smothering aquatic life and otherwise degrading water quality. Without an in-depth analysis of exactly how much spoil will be created and how it can be safely disposed of, the states cannot possibly certify that this pipeline project will comply with the Clean Water Act.”

“Even with Dominion’s refusal to provide the public with adequate information, the situation is clear: The proposed construction plan will have massive impacts to scenic vistas, terrestrial and aquatic habitats, and potentially to worker and resident safety,” said Dan Shaffer, Spatial Analyst with the Dominion Pipeline Monitoring Coalition. “There is no way around it. It’s a bad route, a bad plan, and should never have been seriously considered.”

The full briefing paper is available here.

Appalachian Preservation Project on Facebook

Appalachian Chronicle on Twitter: @appchronicle

Pipeline Monitoring Group: FERC Not Doing Job on ACP

Dominion Pipeline Monitoring Coalition calls for agency to ‘start over and do a proper’ environmental study on the Atlantic Coast Pipeline

By Michael M. Barrick

MONTEREY, Va. – The Dominion Pipeline Monitoring Coalition (DPMC) is again challenging the work of the Federal Energy Regulatory Commission (FERC) regarding the proposed Atlantic Coast Pipeline (ACP). In a news release, Rick Webb, program director for DPMC, said, “If built, the ACP could mar the beautiful, unfragmented viewshed of the southern end of the proposed 90,000-acre Shenandoah Mountain National Scenic Area that stretches from Rt. 250 north to Rt. 33 on the western side of the Shenandoah Valley.”

Shenandoah Mountain

Shenandoah Mountain. Photo by Brad Striebig

He explained, “The Natural Gas Act requires FERC to assess impacts to scenic areas and recreational trails. Yet, the Draft Environmental Impact Study (DEIS) for the ACP does not consider impacts to this special area which was proposed for congressional designation by Friends of Shenandoah Mountain a decade ago, recommended by the 2014 George Washington National Forest plan, and endorsed by over 280 diverse organizations and businesses.”

Webb continued, “In addition, the DEIS ignores impacts to the Wild Oak National Recreation Trail and dismisses Forest Service requests to re-evaluate wild brook trout stream crossings on Hankey Mountain.”

According to Webb, a new utility corridor across the Braley Pond area and Hankey Mountain would:

  • diminish scenic beauty
  • degrade popular recreational resources
  • fragment core forests
  • damage wild brook trout streams
  • industrialize a major gateway to the scenic area

Consequently, he noted, “A permanent corridor of this magnitude could degrade the natural and scenic characteristics of the proposed National Scenic area to the point where it could jeopardize its viability for congressional designation.”

Webb argued that FERC has failed to comply with the National Environmental Policy Act (NEPA). He argued, “In order to comply with NEPA, FERC needs to start over and do a proper DEIS that fully considers significant impacts to one of the largest, mostly unfragmented tracts of national forest land east of the Mississippi River. The proposed scenic area and its water and recreation resources are revered by the public and deserve due consideration in the DEIS.”

Webb noted that the DPMC has created an online Story Map – “Proposed Shenandoah Mountain National Scenic Area and the Atlantic Coast pipeline.”

Learn more about the DPMC here or contact Rick Webb at rwebb.dpmc@gmail

© Michael M. Barrick, 2017

We are on Facebook

On Twitter: @appchronicle

Group: Proposed ACP Pipeline Poses Undue Risks to the Blue Ridge

Too many questions remain for FERC to approve the Atlantic Coast Pipeline says monitoring coalition

By Rick Webb

dpmc-photo

In-stream blasting would be used for crossing the South Fork of the Rockfish River, a native trout stream in the pipeline corridor below the proposed drilling operation.

MONTEREY, VA. – The Dominion Pipeline Monitoring Coalition (CPMC) has submitted a report to the Federal Energy Regulatory Commission (FERC) on the Draft Environmental Impact Statement (DEIS) for the Atlantic Coast Pipeline (ACP) and the proposal to drill through the Blue Ridge Mountains under the Appalachian Trail, the Blue Ridge Parkway, and the National Forest.

The information provided in the DEIS is insufficient to support evaluation of the proposed Blue Ridge drilling operation. The scale of excavation is not fully disclosed or considered, and the results of critical geophysical investigations have not been provided. Identification of geohazards and evaluation of mitigation measures have been deferred until later, precluding a meaningful opportunity for informed review of the project. The published DEIS fails to meet the information needs of the public or the governmental agencies that have responsibilities related to the ACP project.

FERC must release a revised DEIS to:
1)  prove that boring through the Blue Ridge is a practicable option, by providing reliable and complete geophysical data
2)  disclose the extent of land disturbance and water quality damage the proposal would create
3)  include detailed, site-specific plans and pollution control measures for all alternatives for crossing the Blue Ridge.

blue-ridge-parkway-3

The Blue Ridge Mountains. Photo by Michael M. Barrick

The DPMC Report:
A High-Risk Proposal – Drilling Through the Blue Ridge for the Atlantic Coast Pipeline
Story Map Version
Facebook Announcement 

To learn more about the DPMC, visit their website: Dominion Pipeline Monitoring Coalition or contact Rick Webb, Program Coordinator at rwebb.dpmc@gmail.com.

Virginia Officials Agree to Demands from Advocacy Group about Pipeline Deliberations

Dominion Pipeline Monitoring Coalition petitioned state official to make public information about pipeline regulatory reviews

MONTEREY, Va. – On May 5, 2016, the Dominion Pipeline Monitoring Coalition (DPMC) sent a Petition for Writ of Mandamus and Injunctive Relief to Angela Navarro, Virginia Deputy Secretary of Natural Resources, and David Paylor, Director of the Virginia Department of Environmental Quality (DEQ) to compel the state to provide information about regulatory reviews of the Atlantic Coast Pipeline (ACP) and Mountain Valley Pipeline (MVP) proposals. The Petition, prepared for filing in the Virginia Circuit Court in Richmond, describes how state officials have violated duties under Virginia’s Freedom of Information Act (FOIA).

The next day, Friday, May 6th, Deputy Secretary Navarro and Director Paylor responded through their counsel, Assistant Attorney General, David Grandis, indicating that they will provide the requested documents early this week.

JB 2

Pristine streams such as Mill Creek, in Randolph County, W.Va., would be significantly impacted by construction of the Atlantic Coast Pipeline. Photo by Michael M. Barrick.

Before the state indicated it would provide the documents, Rick Webb, DPMC Coordinator, said, “We are disappointed that Virginia’s environmental officials have failed to live up to a law designed to give Virginian’s open access to their own government. Nearly three weeks ago, we asked for public records that would help us and other citizens understand what the State intends to do to protect citizens and the environment from damages the pipelines could cause.” He continued, “Officials are supposed to respond to such information requests within five business days but we received no reply for nearly three weeks. Finally yesterday (May 4) they acknowledged they’d received our letter but did not offer to provide the information we’ve requested.”

The Virginia DEQ has a duty, under the federal Clean Water Act and Virginia Water Protection laws, to review the gas pipeline proposals and ensure that no project goes forward unless all water quality standards will be met, argued Webb. However, as DPMC’s April 14 letter recounts, Virginia DEQ seems to be willing to cover both ACP and MVP under “general permits,” essentially rubber stamping the projects under blanket approvals issued in 2012 and intended only for small projects that pose little risk to waters, Webb argued. DPMC sought public records through the April request to clarify the state’s positions and to question whether the DEQ is able to justify its approach.

The Petition can be accessed here. The FOIA request was included in an April 14th letter, which can be accessed here. The letter objected to the state’s apparent intention to certify the ACP and MVP under general permits issued in 2012. The FOIA request sought information related to the following questions concerning both the ACP and MVP:

1) Has DEQ deemed the Joint Application and/or other information submitted for the projects to be complete and accurate such that DEQ is able to make a formal finding as to the projects’ eligibility for coverage under Virginia’s blanket 401 water quality certification?

2) Has the Corps of Engineers indicated to DEQ that the projects meet the Corps’ requirements for coverage under the general Nationwide Permit 12?

3) Has DEQ made a tentative or final finding that the projects comply with the conditions of the blanket 401 certification for Nationwide Permit 12?

4) Has DEQ requested and/or received additional information from the applicants, in addition to that contained in the Joint Applications, to reveal proposed construction and detailed pollution control methods and analyze possible water quality impacts?

IM000674.JPG

Meathouse Fork in Doddridge County, W.Va. with heavy sediment resulting from pipeline construction in the summer of 2015. This would be the fate of thousands of miles of watershed should the ACP be built. Photo by Michael M. Barrick.

According to DPMC, this is the second time this year that Virginia officials have violated the Freedom of Information Act after DPMC requested records on the gas pipelines. In an earlier case, Carlos Hopkins, Counsel to Governor McAuliffe, failed to provide records within the required period. On March 4, 2016, David Sligh of DPMC wrote Hopkins: “I believe the Governor’s Office is now in violation of the time requirement for response to FOIA requests, under 37 § 2.2-3704. You informed me that the check sent on behalf of DPMC was received at your office on February 15 or 16. Therefore, the records or an appropriate response should have been sent no later than Feb. 23.”  Less than two hours after receiving Sligh’s note, Mr. Hopkins provided the documents but failed to explain the failure to abide by the law.

“This legal action is about much more than an arbitrary deadline or a technicality,” Rick Webb stated: “It’s about the McAuliffe administration’s respect for the rights of citizens trying to play their proper roles and protect their communities and natural resources. The law says a failure to properly respond to a FOIA request is the same as refusing the request outright. We won’t accept a refusal of our rights.”

Deerfield - Augusta County

A screen shot from the DPMC”s new interactive web mapping system. This is of blast radius and evacuation zones for the proposed Atlantic Coast Pipeline. Courtesy DPMC.

New Layers Added to DPMC ACP map, including blast radius and evacuation zones

According to DPMC, additional map layers have been added to the ACP-Environmental Mapping System. Features include:

1) Estimated blast radius and evacuation zone for the proposed ACP.

2) Updated ACP construction corridor and access roads for the 10/30/15 and 4/15/16 submissions to FERC.

3) Direct and core forest loss associated with the proposed ACP construction corridor and access roads.

4) Virginia property parcels.

5) Stream crossings. (Information on crossing methods and environmental factors will be added).

The current version of the ACP-Environmental Mapping system can be accessed via the DPMC website, www.pipelineupdate.org. The link is in the right-hand sidebar.

© Appalachian Chronicle, 2016.

We are on Facebook

On Twitter: @appchronicle

Atlantic Coast Pipeline Costs Outweigh Benefits, Claims Independent Study

Cost to people, communities and environment could run into billions along entire route, based on four-county study

MONTEREY, Va.  – Five groups concerned about the short-term and permanent impacts upon their communities caused by the proposed construction of the Atlantic Coast Pipeline (ACP) have released an independent study revealing that just four counties in Virginia would likely experience billions of dollars of loss and damage should the ACP be built. The report was commissioned by the ACP Highlanders for Responsible Development, Augusta County Alliance, Friends of Nelson, Friends of Buckingham, and Yogaville Environmental Solutions. The exhaustive in-depth study was conducted by Key-Log Economics, a research economics firm based in Charlottesville, Va.

A news release from Allegheny-Blue Ridge Alliance about the study stated, “Dominion says that it would cost approximately $5 billion to build its 594-mile high pressure natural gas transmission line through West Virginia, Virginia, and North Carolina. That number pales in comparison to the costs and economic impacts of the pipeline that will be incurred across just a four-county area of western and central Virginia. …”

The statement continued, “The eye-opening analysis found that up to $141 million in lost property value and services, such as water and air quality, would occur across the four-county study area just during construction. Further, the pipeline will depress area economies, contribute to job loss, reduce quality of life, and lower personal incomes in perpetuity to the tune of up to $109 million annually.”

Those estimates are conservative, notes Spencer Phillips, founder of Key-Log Economics. “Putting the stream of costs into present value terms and adding the one-time costs, the total estimated cost of the ACP in Highland, Augusta, Nelson, and Buckingham Counties is between $6.9 and $7.9 billion,” he said.

Lewis Freeman, Chair of the Allegheny Blue Ridge Alliance and President of Highlanders for Responsible Development, added, “In Highland County annual costs to the local economy are estimated to be $7 million or higher, much larger than the projected benefits that would come to the county, including tax revenues paid by the pipeline. Adverse impacts on property values, which have already been negatively affected by the prospect of the project, will be significant. Also negatively impacted will be travel and tourism, which account for one-fifth of the county’s employment.”

For Augusta County, through which Dominion proposes to run more than 50 miles of the pipeline route, the negative impacts to people’s lives and property is enormous, according to the report. Total property value lost would be approximately $44.5 million, resulting in an annual reduction to the county coffers in excess of $209,061. “Those figures, while conservative and not inclusive of the new route through the Deerfield Valley, are based on loss of subdivision and development potential, loss of property value and property marketability because of proximity to the pipeline, damage to water resources, and a reduction in agricultural production to name just some of the factors that went into the calculation,” noted Nancy Sorrells, Chair of the Augusta County Alliance.

The Atlantic Coast Pipeline would cost Nelson County up to $43 million dollars per year, with additional one-time costs of up to $41 million according to the report. Individuals and businesses would lose up to $25 million in property value outright, while annual losses would include $18 million in recreation tourism dollars and $1.2 million in personal income. The annual loss to the county government would be $526,000 in tax revenue and $144,000 in property tax revenue, far exceeding the local annual tax payment promised by ACP, LLC.

The communities in Buckingham County, the eastern-most county in the study, are faced with the double whammy of the massive pipeline and a gigantic compressor station that will be in operation 24/7. According to the study, the ACP would cost Buckingham as much as $20.8 million in one-time costs and annual losses of as much as $7.1 million.

“I would encourage every Buckingham resident to become familiar with Key-Log’s findings,” noted Chad Oba, Chair of Friends of Buckingham. “This report uncovers previously undisclosed costs of Dominion’s mega-industrial project for our county. No one wants to live near a toxin-belching compressor station nor a 42-inch pipeline, both of which bring many health hazards, and threaten Virginians’ property rights.” As to the purported tax revenue promised by Dominion to the county, she added, “No amount of tax revenue can buy off citizens who are sincere about protecting their community and their beautiful surroundings.”

The pipeline impact study was spearheaded by local citizens groups and property owners who were frustrated at the inaccurate information being distributed by Dominion in regard to the purported benefits of the ACP. Not only were those “benefits,” such as large numbers of jobs during and after pipeline construction and promised tax payments to the counties, generally understood to be greatly inflated, they were also not balanced with information on what the negative effects of the pipeline could be in these central and western Virginia communities.

“It has fallen on us to analyze the costs to our communities should this pipeline come to pass,” said Ernie Reed of Friends of Nelson, the lead group that commissioned the study. “This report demonstrates not only how economically dangerous the pipeline is but how our four counties would bear a huge share of the costs of this project at the hands of Dominion. Further, while the use of the pipeline is measured in years, the costs to the region are forever.”

The study and recent alternate route proposed by Dominion

The statement added, “The recently announced re-routing of the ACP through the southern portion of Highland County, into Bath County, and back through Augusta County was announced after the Key-Log study was completed. While the re-routing would reduce to some extent the economic impact on Highland, the negative economic impact resulting from the re-routing into northern Bath County would increase the total impact on the immediate region due to the higher property values of affected property and businesses in Bath. Further, the additional dozen or so miles added to the Augusta County route will only serve to increase the final economic impact to that community.” It noted, “The uniqueness of the counties in the study mean that the specific impacts within each area vary. However, the underlying result, as pointed out in the study, is that the four counties will be deeply impacted in a very negative way.”

Regarding the proposed alternative route, The Recorder, a weekly newspaper based in Highland and Bath counties, noted that Dominion had originally rejected the alternative route. In this weeks’ edition, published today, the newspaper reported that Dominion rejected the route it is now proposing because, “Crossing this terrain with a 42-inch-diameter pipeline while attempting to minimize or avoid traversing steep side slopes would result in multiple, steeply graded, up-and-down approaches to ridge tops that would in many instances require heavy equipment winching on both sides of the ridge from single or multiple staging areas on the ridge top … Because of the narrowness and remoteness of the ridge tops, most of these areas would require the construction of a graded winching platform on top of the ridge, and depending on the slope, could require construction of an access road along the ridge to access the winch platform for delivery of construction equipment and pipe sections. Access to the remote areas crossed by the three southern alternative routes would be difficult due to the lack of existing nearby roads … which could require the construction of new roads into these areas. Slope restoration and stabilization would also be difficult to achieve in many of the steep areas crossed.”

This is the first independent study done on the ACP. However, when one considers that this study covers only a small portion of the proposed route, it seems rather clear that Dominion is proposing a project that will accomplish only two things – provide additional dividends to its shareholders and destroy all that is dear to the people of Appalachia.

© Michael M. Barrick, 2016

We are on Facebook

On Twitter: @appchronicle

 Related Links

Allegheny-Blue Ridge Alliance and Links to Studies

ACP Highlanders for Responsible Development

Augusta County Alliance

Friends of Buckingham

Yogaville Environmental Solutions

Key-Log Economics

Friends of Nelson

Interactive ACP Environmental Map

Dominion Pipeline Monitoring Coalition

 

Related Articles

Proposed ‘New’ Route for Atlantic Coast Pipeline no Better than one Rejected, Say Opponents

U.S. Forest Service Puts the Brakes on the Atlantic Coast Pipeline

West Virginia Pipeline Project Cited for Numerous Violations

FERC Challenged to be Truly Independent

Proposed ‘New’ Route for Atlantic Coast Pipeline no Better than One Rejected, Say Opponents

Atlantic Coast Pipeline LLC forced to adopt alternative route after U.S. Forest Service rejected recent proposal

By Michael Barrick

CLARKSBURG, W.Va. – The Atlantic Coast Pipeline, LLC (Atlantic) a subsidiary of Dominion Resources, Duke Energy, and others, has filed an alternate proposed route for the Atlantic Coast Pipeline (ACP) with the United States Forest Service (USFS). The new filing comes after the USFS in January rejected the initial proposal brought by Atlantic. Originally planned at about 550 miles, this alternative would bring the total closer to 600 miles, including over some of the most impenetrable mountainous terrain in the eastern United States.

As currently proposed, the ACP would originate near here in Harrison County, and terminate in southeastern North Carolina. Ultimate approval for the ACP will be up to the Federal Energy Regulatory Commission (FERC).

Once again, Dominion has proposed a route without thinking through or understanding the environmental and other consequences of its decision.” – Statement from Allegheny-Blue Ridge Alliance

However, ACP must first gain USFS approval because it wishes to build the pipeline through three national forests in West Virginia and Virginia – the Monongahela, the George Washington and the Jefferson. In rejecting ACP’s original proposal last month, and requiring that a new one be filed, the USFS said the route would cause harm to “ … highly sensitive resources, including Cheat Mountain salamanders, West Virginia northern flying squirrels, Cow Knob salamanders, and red spruce ecosystem restoration area.”

When submitting its alternative plan, Atlantic said, “The route will reduce total mileage in the national forests by more than one-third, from 28.8 miles to 18.5 miles.” It admitted, though, “The alternative route will impact approximately 249 new landowners in Randolph and Pocahontas counties in West Virginia, and Highland, Bath and Augusta counties in Virginia.”

It said also, “We are contacting landowners along the alternative route to request permission to survey their properties so the route can be thoroughly evaluated. Atlantic will submit a preliminary analysis of the route to the FERC next week, and plans to hold a series of public informational open houses along the route in early March.”

Opponents to the ACP, meanwhile, argue that the alternative proposal is no better, for numerous reasons.

Revised ACP route

ACP alternative route is in blue

Marilyn Shifflett of Free Nelson, in Nelson County, Va., said, “To have come forward with such a massive reroute so quickly after the USFS denied permit on the prior route speaks volumes about the lack of consideration for environmental impacts, and impacts to private property owners.” She continued, “The ACP’s new route is equally as devastating, if not more, than their prior route. A significant number of landowners have been impacted, with the hardest hit taken in Pocahontas County, West Virginia, and Bath and Augusta counties in Virginia.”

Rick Webb of the Dominion Pipeline Monitoring Coalition, also based in Virginia, responded, “Dominion fails to recognize … that the real issue is construction of a major pipeline through the greatest concentration of remaining wild lands, pristine streams, and intact ecosystems in the central Appalachian region.”

Webb added, “Although the newly proposed route would reduce impacts to certain species that are emblematic of this wild landscape, Dominion’s alternate route still involves significant forest fragmentation and fails to avoid environmental harm associated with construction across steep mountains and complex karst valleys. Moreover, Dominion is now proposing to build the pipeline along a path that was initially rejected for being too challenging and hazardous.”

He continued, “The proposed ACP is unprecedented with respect to pipeline size and the level of disturbance that will be required. There is no acceptable route for the ACP through the central Appalachian region. The proposed pipeline will be 42 inches in diameter, requiring excavation of an 8- to 12-foot-deep trench and the bulldozing of a 125-foot-wide construction corridor straight up and down multiple steep-sided forested mountains. It will require construction of heavy-duty transport roads and staging areas for large earth-moving equipment and pipeline assembly. It will require blasting through bedrock, and excavation through streams and wetlands. It will require construction across unstable and hydrologically sensitive karst terrain.”

Argued Webb, “Pipeline construction on this scale, across this type of steep, well-watered, forested mountain landscape, is unprecedented. It will be impossible to avoid degradation of water resources, including heavy sedimentation of streams, alteration of runoff patterns and stream channels, disturbance of groundwater flow, and damage to springs and water supplies. It will be impossible to avoid fragmentation and degradation of intact, high-integrity forests, including habitat for threatened and endangered species and ecosystem restoration areas”

A statement issued by the Allegheny-Blue Ridge Alliance, also based in Virginia, noted, “The new alternative route for the Atlantic Coast Pipeline … avoids Cheat and Shenandoah Mountains but compounds the ecological harm that would ensue. By directing the pipeline further south in Pocahontas County, W.Va., into northern Bath County, Va. and then north through the Deerfield Valley in Augusta County, the route would traverse some of the most concentrated karst topography in the Allegheny region. A pipeline through this area would significantly increase the likelihood of catastrophic erosion and sediment pollution of several significant waterways. Furthermore, the new route opens up to potential devastation a whole new set of cultural and natural resources. The many newly affected landowners and local officials must be carefully consulted before the project should be allowed to continue with the FERC process.”

The group added, “Once again, Dominion has proposed a route without thinking through or understanding the environmental and other consequences of its decision.”

Tom Berlin, a farmer in Lewis County, W.Va., said that he believes, in the end, the ACP will be approved. “I think they will keep finding alternatives until they get the opposition worn down and FERC may make them jump through a few more hoops. Eventually, governors, representatives, and senators will decide that they have had enough and pressure FERC and the Forest Service to approve the project. There is the pressure of appropriations to get compliance. I feel that ACP will be built and we can only hope to minimize damage and get the best possible deal for local landowners.”

Dianna Gooding, a farmer in Gilmer County, W.Va., which neighbors Lewis County , offered, “First,  the proposed alternative I believe is the original route that was also opposed early on,  and that it was decided that the terrain was too steep,  too rocky etc., and disrupted too many landowners. The overall impact will be just as bad if not worse and will of course affect many more private landowners.” She shared also that while the Stonewall Gas Gathering line was being constructed last year, a supervisor with one of the involved companies said “… they had made plenty of mistakes, the terrain was something they had never worked in before, and they were flatlanders primarily. They had many, many issues, and the other companies were not knowledgeable either about building such large lines in the terrain. …”

Senior Attorney Greg Buppert with the Southern Environmental Law Center said, “Dominion has proposed a knee-jerk and ill-conceived adjustment to its favored route, rather than a solution that truly attempts to minimize the harm to this region. To prevent unnecessary impacts to our communities and environment, we must understand whether the Atlantic Coast Pipeline is truly needed to meet the regional demand for natural gas in light of the changes to existing pipelines that are already poised to bring more gas into Virginia,” He added, “The new route also raises fundamental questions of fairness. FERC must put the Atlantic Coast Pipeline on hold until the citizens of Bath County and other communities along the route have the same opportunities as others along the pipeline route to understand the project, evaluate its impacts, and make their voices heard.”

Ben Luckett, Staff Attorney with West Virginia-based Appalachian Mountain Advocates, stated, “This new route would still cause dramatic forest fragmentation through some of the most high-quality forest habitat in our region.” He added, “We’re disappointed Dominion would threaten a whole new set of Virginians and West Virginians when the pipeline is not even necessary to meet our energy needs.”

Concluded Shifflett, “Dominion will try to push this new route through quickly to maintain their construction schedule, and the FERC will likely not ask for a fair time frame for residents to respond, unless there is a massive public outcry. We need to continue our solidarity in West Virginia and Virginia to ensure that we are heard and a fair process is offered to every landowner.”

© Michael M. Barrick, 2016

We are on Facebook

On Twitter: @appchronicle

Related Links

Interactive ACP Environmental Map

Allegheny-Blue Ridge Alliance

Dominion Pipeline Monitoring Coalition

Southern Environmental Law Center

Appalachian Mountain Advocates

 

Related Articles

U.S. Forest Service Puts the Brakes on the Atlantic Coast Pipeline

Seeking Dominion over His Own Land

West Virginia Pipeline Project Cited for Numerous Violations

FERC Challenged to be Truly Independent

Ecological Monitoring Group Challenges Virginia Governor to be Transparent about Pipeline Deliberations

Virginia-based Dominion Pipeline Monitoring Coalition request documents that relate to directives from Governor Terry McAuliffe to state employees about the Atlantic Coast and Mountain Valley Pipelines

RICHMOND, Va. – The Dominion Pipeline Monitoring Coalition (DPMC) has filed a request with Governor Terry McAuliffe for documents that relate to the Atlantic Coast and Mountain Valley Pipelines. The request, filed under Virginia’s Freedom of Information Act (FOIA), asks for all pipeline-related documents in the governor’s office that have been sent between Virginia state agencies and the governor’s office and any sent between companies associated with the two pipeline proposals and the governor.

The Roanoke Times recently reported that Governor McAuliffe “…wants state agencies to brief his office before department employees comment publicly about two deeply controversial interstate natural gas pipeline projects that have received the governor’s blessing.”

According to Rick Webb, Coordinator of the DPMC, “That (newspaper) report sparked citizen concerns that essential findings and opinions from scientific and regulatory experts in Virginia government may not reach the public or may be changed before release. The fact that the governor joined Dominion Power officials to tout the Atlantic Coast Pipeline before any state environmental or safety reviews could be begun, let alone be completed, heightened these citizen concerns.”

David Sligh, a Senior Regulatory Systems Investigator with DPMC, who filed the request with Governor McAuliffe, wrote “[w]e and the many thousands of individuals, along with numerous organizations and local government bodies who have serious concerns about the ways these pipelines would affect communities and the environment depend on you to protect our interests but also accept the responsibility to be vigilant and involved actors in public decisional processes. We know that you support our rights to do so and trust you will act to allow us to exercise those rights.”

The Virginia General Assembly, in enacting the FOIA, wrote that “[t]he affairs of government are not intended to be conducted in an atmosphere of secrecy since at all times the public is to be the beneficiary of any action taken at any level of government” and they stated a goal “to promote an increased awareness by all persons of governmental activities and afford every opportunity to citizens to witness the operations of government.”

Webb said, “If provided the information requested, DPMC will use it to play our proper role in our government and will make it available to our fellow Virginians. We ask now that the governor work with us to ‘promote an increased awareness’ in the state’s activities related to the Atlantic Coast Pipeline and the Mountain Valley Pipeline.”

He continued, “We ask the governor to provide access to all of the requested information, and to live up to commitments he made before taking office. As Governor-elect, Mr. McAuliffe pledged to set a new standard of ‘transparent, accountable, state government that is beholden only to the taxpayers who fund it… .’ Virginians should never have to question who their leaders are putting first.”

Groups Work to Bring the Public Voice into Gas Pipeline Projects

Coalition seek answers from WV Department of Environmental Protection

CHARLESTON, W.Va. – Members of a coalition of groups including West Virginia Highlands Conservancy, West Virginia Rivers Coalition, and the Dominion Pipeline Monitoring Coalition commissioned the consulting firm Downstream Strategies to investigate public input opportunities related to the onslaught of proposed natural gas pipeline construction projects across the state. Special focus is given to one of the proposed large-scale interstate transmission lines, the Atlantic Coast Pipeline – a 42” diameter pipe set to cross a total of 100 water bodies within West Virginia.

“The pace of new pipeline development in West Virginia is overwhelming,” said Cindy Rank, of West Virginia Highlands Conservancy. “Residents are concerned about the damage they’re already seeing to their land and local streams, so we’re working to be able to better educate ourselves and others about the West Virginia Department of Environmental Protection’s (WVDEP) role in the permitting process.”

The groups’ initial research resulted in a report released recently, “Atlantic Coast Pipeline in West Virginia: Opportunities for Public Engagement regarding Erosion and Sedimentation,” and is available at www.wvrivers.org/archive/pipelinereportdownstreamstrategies.pdf. Erosion and sedimentation causes nearby waterways to be unnaturally muddy to the point of impacting stream life.

“The rush to build pipelines raises serious concerns for water quality,” said Angie Rosser, executive director of West Virginia Rivers Coalition. “We’re seeing that efforts to control run-off and slides from these projects aren’t working and our streams are paying the price.”

The report lays out points for public participation in decision-making around the Atlantic Coast Pipeline; however it presents as many unanswered questions as answers. The coalition of groups is committed to seeking clarification from the WVDEP on the state’s storm water permitting process for natural gas pipeline construction.

“Although pipeline companies promise to comply with regulations and avoid impacts to landowners, the reality on the ground is quite different,” said Rick Webb, Coordinator of the Dominion Pipeline Monitoring Coalition. “The companies show very little respect for either people or the environment. The fines they sometimes pay are simply the cost of doing business. It seems that non-compliance is cost effective.”

An example of fines for non-compliance came last week when WVDEP agreed to a settlement in which MarkWest Liberty Midstream & Resources will pay $76,000 in fines for a long list of water pollution violations related to at least five of its pipeline projects.

Groups involved in these efforts include Dominion Pipeline Monitoring Coalition, Greenbrier River Watershed Association, WV Highlands Conservancy, WV Rivers Coalition and others.